How to Read a Remodeling Estimate, and What Illinois Law Requires
Why three bids for the same kitchen differ by 0,000, the six lines that explain a cheap quote, and the protections Illinois law already gives you.
Three contractors walk through the same kitchen. One quote comes back at $52,000, one at $71,000, one at $38,000. They are all for “a kitchen remodel.” Nothing in the three documents lets you compare them, and that is not an accident.
“Why are these bids so far apart, and which one is real?”
Almost always the spread is not craftsmanship. It is scope, allowances, and what has quietly been left out. At ADS Building & Remodeling we bid work in Buffalo Grove, Arlington Heights, Glen Ellyn, Naperville, Wheaton, and Schaumburg, and we lose bids to numbers that later grow. Here is how to read the paperwork so that does not happen to you.
What Illinois Law Already Gives You
Before anything else, know the floor you are standing on. Under the Illinois Home Repair and Remodeling Act, for residential work over $1,000:
- The contractor must obtain a signed written contract or work order before starting work or charging for it.
- The contractor must give you a copy of the state pamphlet “Home Repair: Know Your Consumer Rights” before the contract is signed, and have you sign an acknowledgment that you received it.
Violations fall under the Illinois Consumer Fraud and Deceptive Business Practices Act. A contractor who shrugs at this requirement is telling you something about how they handle the rest of their obligations.
The Six Lines That Explain a Cheap Bid
1. Allowances
An allowance is a placeholder. “Tile allowance: $4 per square foot” means the price you were quoted assumes the cheapest builder tile at the store, and everything you actually like is extra. Allowances are the number one reason a $38,000 kitchen becomes a $55,000 kitchen.
What to ask: list every allowance and what it assumes. Better still, make your selections before signing so the contract carries real prices instead of guesses.
2. Demolition and Disposal
Dumpsters, hauling, and the labor of tearing out are real money. On a full kitchen it is commonly $1,500 to $4,000. If you cannot find it in the document, it is either buried or missing.
3. Permits, Drawings, and Inspections
Permit fees vary widely between suburbs and can run from a few hundred dollars to a few thousand on structural work, plus engineering if a wall is coming out. A bid that omits permits is not cheaper. It is a bid to do the work without them, which becomes your problem at resale.
4. Electrical and Plumbing to Current Code
Open a 1970s kitchen wall and you will often find circuits that were legal then and are not now. Kitchen counter receptacles, GFCI and AFCI protection, dedicated appliance circuits, venting corrections. Ask directly: does this bid assume existing electrical and plumbing are reused as-is, or brought to current code?
5. Drywall, Paint, Trim, and Flooring Transitions
The unglamorous finish work is where thin bids get thin. Patching the ceiling where a soffit came out, painting the adjacent wall so it does not stop at a corner, and the threshold where new floor meets old are all real line items.
6. Project Management and Warranty
Somebody has to sequence twelve trades, order material on time, and come back when a drawer sags in month five. A bid with no overhead line either has it hidden, or has no one doing that job.
What a Good Contract Contains
- Itemized scope by area, written so a stranger could walk the house and tell whether it was done.
- A payment schedule tied to milestones, not to dates. Money follows completed work.
- A change order clause requiring written approval and a price before extra work begins.
- Named products, models, and colors, or a documented selection list attached.
- Start and substantial completion dates, with what happens if they move.
- Proof of insurance, general liability and workers compensation, sent directly from the insurer.
- Lien waivers from the contractor and any subcontractor or supplier at each payment.
- A written warranty period on workmanship, separate from manufacturer warranties.
Lien Waivers Deserve Their Own Paragraph
In Illinois, subcontractors and suppliers who are not paid can place a mechanics lien on your home even if you paid your contractor in full. The protection is simple and most homeowners never ask for it: collect a signed lien waiver with each payment, covering the work paid for. Any legitimate contractor does this routinely. It costs nothing and it is the difference between a paperwork step and a legal problem.
The Deposit Question
A reasonable deposit funds material orders and secures a slot on the calendar. Something in the range of 10 to 30 percent is normal for a remodel of any size, with the balance tied to milestones.
What should make you uncomfortable: more than half the contract price before work begins, a demand for cash, a large discount for paying everything up front, or pressure to sign today because pricing expires tonight. Those are not financing arrangements, they are risk transfers.
Five Questions That Sort Bidders Fast
- What is not included in this price that a typical project like mine ends up needing?
- Which parts are your own crew and which are subcontracted?
- What happens to the schedule and the price if you open a wall and find something?
- Can I see two projects you finished in the last year, in a home like mine?
- Who do I call on a Tuesday when a question comes up, and how fast do they answer?
The answers are more predictive than any number on the front page.
Common Questions
Is the lowest bid always a bad sign?
No. Sometimes a company has an efficient crew and a gap in the schedule. But when a bid is 25 percent under two others, it is nearly always a different scope rather than a better deal, and comparing line by line makes that visible in ten minutes.
Should I pay for a detailed estimate?
Some firms charge for a full design and detailed takeoff, and that is legitimate work. At ADS the in-home consultation, the design conversation, and the 3D rendering are complimentary.
What if the price changes mid-project?
It should only change through a written change order that you approve before the work is done. Our quotes are fixed after signing, and the only thing that moves the number is a change you ask for or a condition behind the wall that we price and present to you in writing first.
Getting Bids This Month?
If you are collecting quotes in Buffalo Grove, Arlington Heights, Glen Ellyn, Naperville, or a nearby Chicago suburb, ask every bidder for the same itemized format. The comparison becomes obvious once the documents describe the same work.
At ADS Building & Remodeling, we provide:
- A complimentary in-home consultation and 3D rendering
- Itemized scope with selections priced in, and no open allowances
- A fixed-price quote that doesn’t move after you sign
- Licensed, insured work with permits, inspections, and lien waivers handled properly
The best protection in remodeling is not a lower price. It is a document specific enough that nobody has to remember what was promised.